If you could peek inside the new Wildwood Library right now, you’d see a buzz of activity.
The wall framing is complete, and drywall is being finished up this week. The window frames are also installed, and will have glass in them soon.

And although it may be a little less exciting than walls and windows, the mechanical system, plumbing, and electrical system are all being installed.
Over the next month, contractors will work on installing the wood ceiling and fire place tile. They’ll also start putting paint on the walls!

Watch Construction Online
Washington County has installed a camera at the Wildwood Library site to show construction progress. The camera will be in place until the library is complete in summer 2020.